Impact DEA have the processes and capacity to manage a roll out of power and data cabling across multiple sites, to deadline and budget. The IP upgrade project is another great example.

The IP upgrade project was undertaken to facilitate the upgrade of Telstra Services within the venue network to the Telstra NextIP Network. Our services for this project included:

  • An audit at each venue
  • Schedule and resource up to 8 teams each week
  • Install new data cabling and a communications rack
  • Provide weekly reports

Impact Data Electrical attended over 250 venues over a 6 month period. We planned a schedule, resourced the project and delivered on time and on budget.

We were trading as SJA Services at the time and it’s nice to come across our SJA stickers on old R&R racks and on the Onelink racks in many venues today.

With full time administrative staff and experienced electrical staff, we can plan and manage your next cabling roll out.